Things have changed again. The construction zone on the east side of 9th Street between K Street and L Street has changed again. The east parking lane and east travel lane are now dedicated to the construction project, the general purpose lane has been shifted right into the west parking lane, and the combined pedestrian/bicyclist bypass is now in what was the right hand general purpose lane.
One the plus side, detectable strips have been added to the left side of the bypass, which are required to provide protection from trip and crash hazards presented by the fence bases. Photo below.

The entrance to the bypass is still awkward, too narrow and poorly signed. There are still corrections to be made.

Previous posts: 9th Street update, 9th St fixed, sort of, and 9th St blocked by construction.
[…] purpose lane. The bypass can be created with use of orange construction barrier, as was done on 9th Street. This bypass would remain in place until construction is […]
LikeLike
[…] 9th St update […]
LikeLike